Variation Order Template

A change that is not confirmed in writing is a change you may never be paid for. This reference format records the scope, the price basis and the time impact before the work is done.

STRUCARCH TEMPLATE · SAMPLE · REFERENCE FORMAT · NOT AN OFFICIAL GOVERNMENT FORM

VARIATION ORDER

VO No: ____   |   Date: ____

Project__________Contract No.__________
Contractor__________Client__________
Engineer / Consultant__________Related BOQ Item / Location__________

1. Description of the change

__________

2. Reason for the change

(design change / site condition / omission / addition / client request / other) __________

3. Basis of pricing

ItemDescriptionUnitQuantityRate (Rs)BasisAmount (Rs)
VO-01______________________BOQ rate / agreed rate / rate analysis____
VO-02____________________________________
Total value of this variationRs ____

4. Time impact

Planned completion impact: ____ days   |   Requests extension of time? Yes / No   |   EOT No. (if applicable): ____

5. Approvals

Contractor

Signature: ______    Date: ______
Engineer

Signature: ______    Date: ______
Client

Signature: ______    Date: ______

Attach rate analysis where the rate is not from the BOQ. Confirm the change in writing before starting the work wherever possible.

When to use this form

  • An instruction changes the drawings, quantities or specifications
  • Extra or non-schedule items are introduced on site
  • Work is omitted, and the contract allows a deduction for the omission
  • The change also affects the programme, so an EOT notice is triggered

Full process explained in contractor billing & IPC and claims & EOT documentation. Price new items with the rate analysis and calculator tools.

More resources

Pair this with the rest of the record

A variation only becomes payable when the surrounding records support it.

Running Bill / IPC

Where the variation value lands in your monthly billing.

Open the template

Measurement Sheet

Measured quantities for the changed or added work.

Open the template

Daily Progress Report

Evidence of when the changed work was done.

Open the template