The monthly billing statement a contractor submits so the Engineer can certify payment. Copy the structure below, fill in your project numbers, and keep a copy for every submission.

STRUCARCH TEMPLATE · SAMPLE · REFERENCE FORMAT · NOT AN OFFICIAL GOVERNMENT FORM

RUNNING BILL / INTERIM PAYMENT CERTIFICATE

Bill No: ____   |   Period: ____ to ____   |   Date: ____

Contractor / Firm__________Contract No.__________
Project / Work__________Client__________
Engineer / Consultant__________Location__________

1. Value of Work Done this Period

Item Description Unit Quantity Rate (Rs) Amount (Rs)
BOQ-001Earthwork in excavationcft
BOQ-002PCC 1:4:8 in foundationcft
BOQ-003RCC 1:2:4 with steelcft
 (add BOQ lines and measured quantities from measurement sheets)    
Total value of work this periodA

2. Deductions

DescriptionBasisAmount (Rs)
Retention money (__%)Clause ____
Mobilization advance recoveryClause ____
Materials / supplies issuedStore issue records
Total deductionsB

3. Summary

Value of work this period (A)Rs ________
Less: total deductions (B)Rs ________
Less: prior certified paymentsRs ________
Net amount claimed this periodRs ________

4. Certification

Prepared by (Contractor)

Name: ______    Signature: ______    Date: ______
Checked / Certified by (Engineer)

Name: ______    Signature: ______    Date: ______

Attach: measurement sheets, rate analyses for extra items, material on site statement, and this bill's progress photographs. Every quantity must trace to a signed measurement record.

What makes this bill pass the Engineer's review

  • Every quantity has a measurement sheet signed by both parties
  • Rates match the BOQ or have an approved rate analysis behind them
  • Deductions follow the contract clauses, not habit or memory
  • The bill is dated, numbered and submitted on time under the contract
  • Changed work carries a variation order or confirmed instruction

See how this all fits together in the contractor billing & IPC service. Need the numbers done for you? Use the engineering calculators or ask Struc-Arch to prepare the bill.

More resources

Build your full document kit

One document alone does not win a billing dispute. Pair the running bill with the records that support it.

Measurement Sheet

The signed record of measured quantities behind every bill line.

Open the template

Variation Order

Confirms instructed changes so they become payable, not disputed.

Open the template

Daily Progress Report

The dated site record that supports quantities, delays and claims.