Contractor Claim Template

A claim that is not documented on time is a claim that may be lost. This reference format structures the entitlement, the event, the delay and cost impact, and the evidence, so the claim is professional and defensible.

STRUCARCH TEMPLATE · SAMPLE · REFERENCE FORMAT · NOT LEGAL ADVICE

CONTRACTOR CLAIM

Claim No: ____   |   Date: ____   |   Type: Time / Money / Both

Project__________Contract No.__________
Contractor__________Client__________
Engineer / Consultant__________Contract Form (FIDIC / PEC / Other)__________

1. Basis of entitlement

Contract clause(s) relied on: __________

Why the contractor is entitled under the contract: __________

2. Event description

What happened, when it happened, and who was responsible: __________

3. Notice chronology

DateNotice / DocumentRecipientReference No.
____Notice of event (issued within contract period?)________
____Initial claim notice________
____Full claim submission________
Attach copies of all notices and correspondence.

4. Delay analysis (if claiming time)

Original completion date: ____   |   Revised / expected completion: ____   |   Days claimed: ____

ActivityPlannedActualDelay (days)Critical path?Cause / responsibility
________________Yes / No____
________________Yes / No____
Attach programme extract, daily reports and correspondence supporting the analysis.

5. Cost assessment (if claiming money)

ItemDescriptionUnitQuantityRate (Rs)Amount (Rs)
C-01Additional labour / plant / material________________
C-02Prolongation / overhead costs________________
C-03Other contract-entitled cost________________
Total claimedRs ____

6. Attachments

Daily reports, letters, instructions, programme, measurements, invoices, witness statements, photographs: __________

7. Declaration

Contractor

Signature: ______    Date: ______
Engineer

Signature: ______    Date: ______

This is a technical documentation reference format. It is not legal advice. Where legal representation is required, engage a qualified legal professional separately.

When to use this form

  • A delay event affects the completion date and an EOT is warranted
  • Additional cost arises from an event that is not the contractor's fault
  • A payment or quantity dispute needs a structured, evidenced submission
  • A deadline in the contract requires a claim to be submitted on time

Full process explained in claims & EOT documentation and contractor billing & IPC. See the construction contracts guide for the FIDIC vs PEC basis.

More resources

Pair this with the rest of the record

A claim is only as strong as the evidence that surrounds it.

Daily Progress Report

Evidence of what happened and when on site.

Open the template

Measurement Sheet

Measured quantities behind the claimed amounts.

Open the template

Variation Order

For instructed changes that are priced, not claimed.

Open the template

Need a claim prepared and documented properly?

Struc-Arch prepares technical claim files: delay analysis, cost assessment, notice chronology and expert documentation. Engineering and technical only, not legal representation.