An EOT claim is won in the file room, not the meeting room. The documents prove three things: that a delay event happened, that it was not your fault, and that it actually pushed the completion date.
Every extension of time claim follows the same documentary chain: notice, records, impact. If one link is missing, the claim is weakened - and a late notice can kill it outright under FIDIC-style contracts.
Most contracts (including FIDIC Sub-Clause 20.1) require the contractor to give notice of a delay within 28 days of becoming aware of it. The notice does not need to be a claim - it simply flags the event and that time is likely to be affected. Late notice can bar the claim entirely, so this is the single most important document.
The final document is the analysis itself: a before/after programme or an as-built versus as-planned comparison showing how many days the delay event pushed the completion date. This is where a structural delay analysis is prepared - usually a time-impact analysis placing each event on the critical path at the time it occurred.
International forms: FIDIC Sub-Clause 8.4 (Extension of Time) and 20.1 (Claims). Pakistani public works commonly use PEC/PPRA-based conditions with similar notice requirements. The delay analysis method (impacted as-planned, time impact, as-built) should follow the contract and accepted practice. Use our claim template as the submission skeleton.
Common questions about time claims under Pakistani contracts.
Under FIDIC 20.1 the failure to give notice in time can bar the claim. Some contracts are interpreted more leniently, but you should never rely on that - the notice is the cheapest document in the entire claim and the one you cannot retrofit.
An EOT gives time. Money for prolongation (site overheads, machinery, staff) is usually a separate head, often payable only for employer-caused delays and only if the contract allows. Time and cost are separate claims.
The Engineer under the contract assesses the claim against the programme and the delay analysis and recommends a decision; the Employer usually confirms. If the Engineer does not decide within the contract period, the contractor can escalate to dispute resolution under the contract.
Related: claims & EOT support service · EOT claim template · construction contracts · more in the knowledge base.
Struc-Arch reconstructs delay records, runs the delay analysis and prepares the full EOT submission for contractors.