PMP · LEED Green Associate · Civil & Structural Engineer - Gujranwala, Pakistan

What Documents Are Required for an EOT Claim?

An EOT claim is won in the file room, not the meeting room. The documents prove three things: that a delay event happened, that it was not your fault, and that it actually pushed the completion date.

Contracts & Claims

The evidence an EOT claim needs

Every extension of time claim follows the same documentary chain: notice, records, impact. If one link is missing, the claim is weakened - and a late notice can kill it outright under FIDIC-style contracts.

1 - The delay notice

Most contracts (including FIDIC Sub-Clause 20.1) require the contractor to give notice of a delay within 28 days of becoming aware of it. The notice does not need to be a claim - it simply flags the event and that time is likely to be affected. Late notice can bar the claim entirely, so this is the single most important document.

2 - The programme

  • The baseline programme - the approved plan at contract start.
  • The updated programme at the time of the delay - showing what was actually happening.
  • A critical path is essential: a delay to non-critical work does not extend completion.

3 - Site records that prove the event

  • Daily site reports / supervisor logs (see our daily report template).
  • Workforce, plant and material return sheets.
  • Photographs and videos with dates.
  • Weather records (rain, storms) for weather-caused delay.
  • Testing reports, approval delays, and RFI/response registers.

4 - Correspondence

  • Letters and emails to/from the Engineer and Employer.
  • Minutes of site meetings and progress meetings.
  • Instructions and variation orders that changed the work.
  • Drawing issue registers - late drawings are a classic excusable delay.

5 - The impact assessment

The final document is the analysis itself: a before/after programme or an as-built versus as-planned comparison showing how many days the delay event pushed the completion date. This is where a structural delay analysis is prepared - usually a time-impact analysis placing each event on the critical path at the time it occurred.

Common mistakes

  • No notice, or a notice sent months late.
  • No updated programme, so the critical path cannot be shown.
  • Claiming days for delays that were never on the critical path.
  • Submitting the claim without any contemporaneous records to back it.

Standards that apply

International forms: FIDIC Sub-Clause 8.4 (Extension of Time) and 20.1 (Claims). Pakistani public works commonly use PEC/PPRA-based conditions with similar notice requirements. The delay analysis method (impacted as-planned, time impact, as-built) should follow the contract and accepted practice. Use our claim template as the submission skeleton.

Frequently Asked Questions

Common questions about time claims under Pakistani contracts.

Can I still claim EOT if I missed the 28-day notice?

Under FIDIC 20.1 the failure to give notice in time can bar the claim. Some contracts are interpreted more leniently, but you should never rely on that - the notice is the cheapest document in the entire claim and the one you cannot retrofit.

Does an EOT also give the contractor extra money?

An EOT gives time. Money for prolongation (site overheads, machinery, staff) is usually a separate head, often payable only for employer-caused delays and only if the contract allows. Time and cost are separate claims.

Who decides whether the EOT is granted?

The Engineer under the contract assesses the claim against the programme and the delay analysis and recommends a decision; the Employer usually confirms. If the Engineer does not decide within the contract period, the contractor can escalate to dispute resolution under the contract.

Related: claims & EOT support service · EOT claim template · construction contracts · more in the knowledge base.

Need an EOT claim prepared from your records?

Struc-Arch reconstructs delay records, runs the delay analysis and prepares the full EOT submission for contractors.